Dixie Highway Viaduct Construction 2026

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

DIXIE HIGHWAY VIADUCT CONSTRUCTION

June 1, 2026 -- While construction was originally anticipated to begin earlier this spring, the Village has now received confirmation from contractor Iroquois Paving of Watseka, Illinois, that work will officially begin Monday, June 1, 2026.

The full 90-day closure of the Dixie Highway North Viaduct is scheduled to begin on June 8, 2026. Construction is anticipated to continue through approximately October 2026.

Prior to and during the closure, IDOT will coordinate efforts to ensure detour routes are clearly posted in advance. Village staff will continue closely monitoring the project and related traffic impacts throughout construction.

Additional public notifications and reminders will be distributed through Village communication channels, including social media, the Home Sweet Homewood app and Rave alerts.

We appreciate the community’s continued patience as this important infrastructure project moves forward.

 New Map - Dixie Highway Viaduct Closure - Village of Homewood (1)

Southbound Dixie Highway Detour:
➡️ Dixie Highway
➡️175th Street
➡️ Governors Highway
➡️ 183rd Street
➡️ Return to Dixie Highway

Northbound Dixie Highway Detour:
➡️Dixie Highway
➡️Ridge Road
➡️ Ashland Avenue
➡️ 175th Street
➡️ Halsted Street
➡️ 171st Street
➡️ Return to Dixie Highway